Physical Verification Report of CHIKTAN Village
Village
CHIKTAN
Block
SHAKAR-CHIKTAN
District
KARGIL
Report By
JE
Date of Inspection
3rd May, 2023
Water Supply Scheme
WSS CHIKTAN
Notes

To ensure the  quality of JJM works and speed up th scheme severe agencies of JJM including Xen PHE, AEE, JE, TPI, ISI, SDM, SARPANCH AND PRI Member  conduct physical inspection of WSS Chiktan.  During the inspection the concerened officers check various aspects such as the quality of material used, adherence to design specifications. they also assess the progress of work and ensure that it is completed within the scheduled times. Overall the physical inspection conducted by the agencies/officers play a significsnt role in improving the quality of JJM works and speeding up the schemes implementation.